2014年8月5日星期二

India power transformer 2MVA inspection


Skype: mark2002719  email : mark@cncele.com

 Our india customer come to our factory to make the visual inspect of the oil immersed power transformer S11-2000. According to customer requirement , we make test :
1. Ratio of winding
2. No load current
3. no load losses
4.load losses
5. power frequency withstand
6. vetocr group verification and induced withstand voltage .

All the test have passed and meet the technical requirement well . As the order is very special in voltage and terminal . There have 13 tap changer and need terminal cover in the up of power transformer . This power transformer will be used in hydro power project in indonesia and we give 1 year quality warranty .